`oxmpl` - sprint-002

Sprint 002 — Release 0.8.0 "Toolchain refresh"

Commitment

The stories committed this sprint (live status in TaskNotes under tag #oxmpl/sprint/002):

Order: S3.1 → S3.2 / S3.3 (either order) → S3.4 → S3.5 → S3.6. One sprint = one release.

Owner-only prerequisites (before S3.6): register trusted publishers on pypi.org (oxmpl-py) and crates.io (oxmpl, oxmpl-py, oxmpl-js) for the exact workflow files and job names.

Capacity risk (flagged at planning)

The commitment is 4×M + 2×S against 1–3 stated sessions in the first two weeks. Sprint-001 ran 2.4× its plan with 2×M. The owner chose all of E3 over three weeks. Checkpoint Wed 2026-10-21: if S3.1–S3.3 are not done by then, the PM will put up one replan sitting (per oxmpl - planning § Mid-sprint scope changes). The likely cut is S3.4–S3.6 into sprint-003, with the goal reduced to "all three bindings green on current dependencies".

Progress log

Review & retro